Question: 7 . 1 2 . For an M / M / 1 queing system with the average interarrival time of 5 minutes and the (
For an MM queing system with the average interarrival time of minutes and the
a the expected response time;
b the fraction of time when there are fewer than jobs in the system;
e the fraction of customers who have to wait before their service starts.