Question: 7 1 point If BAC is $ 2 0 0 , 0 0 0 , Duration is 2 2 0 days, PV is $ 6

71 point
If BAC is $200,000, Duration is 220 days, PV is $62,000,% Complete is 29%, and AC is $59,000, what is the state of the project?
Under budget, ahead of schedule
Over budget, behind schedule
Under budget, behind schedule
Over budget, ahead of schedule