Question: 7 1 pts Your team's project has fallen slightly behind schedule and will incur late penalties unless the project can be brought back on schedule.
7 1 pts Your team's project has fallen slightly behind schedule and will incur late penalties unless the project can be brought back on schedule. Which of the following actions would be most appropriate in this situation? Eliminate non-critical-path activities because they aren't that important. Renegotiate the deadline with the project sponsor/customer. O Crash or shorten the duration of those activities on the critical path that are next in line (to be completed). Crash or shorten the duration of those activities on the critical path with the lowest per-period crashing costs. Question 8 1 pts A Gantt chart provides better visibility of interdependencies than a network diagram (especially when the project has many tasks). O True 4 False