Question: 7 . 3 A project requires 4 0 , 0 0 0 cy of compacted fill that must be completed in 3 2 work -
A project requires cy of compacted fill that must be completed in work ing days. The fill material will be hauled to the site in cy loose measure, trucks. The cycle time for a truck is min per trip. The swell factor for the earth is and the shrinkage factor is Assume hours per day and a min effective hour. Determine the number of required trucks to complete the project in days.