Question: 7 60 to 0 Lead Time: 3 weeks Week 1 2 3 4 5 6 8 Gross 35 20 10 25 40 40 requirements 60

7 60 to 0 Lead Time: 3 weeks Week 1 2 3 4 5 6 8
7 60 to 0 Lead Time: 3 weeks Week 1 2 3 4 5 6 8 Gross 35 20 10 25 40 40 requirements 60 Scheduled 70 receipts Projected on-hand 10 45 25 15 Inventory Planned 0 0 10 40 40 60 receipts 60 Planned order 10 40 40 60 60 0 reienses C. Complete the last three rows of the record by using the POQ Ist-sizing rule, with P=4. (Enter your responses as integers. A response of o" is equivalent to being not applicable) Item: Driveshaft subassembly Lot Size: POQ (P=4 Lead Time: 3 weeks Wook 4 5 6 7 8 Gross 35 requirements 20 10 25 40 40 Scheduled 70 receipts Projected on hand 10 Inventory Planned receipts 1 2 3 - N 60 60

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!