Question: 7 a. Duration (weeks) Most Pessimistic Activity Predecessor Optimistic Likely A 2 4 B A 2 3 7 A 5 D B 3 6 9

7 a. Duration (weeks) Most Pessimistic Activity

7 a. Duration (weeks) Most Pessimistic Activity Predecessor Optimistic Likely A 2 4 B A 2 3 7 A 5 D B 3 6 9 E 2 Calculate the expected F A 4 5 7 time (te) for each activity. G E, F 4 8 b. Draw an Activity on H D 2 3 Node (AON) diagram to I G H 2 4 6 reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. d. Calculate the slack for each activity. e. Identify all activities on the Critical Path. f. Use the data to calculate the probability the project will finish in 20 weeks (Hint: Z-score). w C

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!