Question: 7 . A project manager is assigned to a 1 2 - month project that has a $ 1 0 0 , 0 0 0
A project manager is assigned to a month project that has a $ budget. Six months have passed and $ has been spent. On closer inspection, the project manager finds out that so far, only of the work has been completed. The value of the completed work is referred to as:a Planned value.b Earned value.c Actual cost.d Cost variance.