Question: 7. A projects free cash flows are expected to be $29,000 annually for 4 years. It will cost $55,000 to start. What is the projects
7. A projects free cash flows are expected to be $29,000 annually for 4 years. It will cost $55,000 to start. What is the projects discount payback if the interest rate is 12%?