Question: 7. Calclulate the expected time for the following tasks: Task Optimistic Time Most Likely Time Pessimistic Time Expected Time A 5 3 7 B 4

7. Calclulate the expected time for the following tasks: Task Optimistic Time Most Likely Time Pessimistic Time Expected Time A 5 3 7 B 4 5 6 c 3 2 1
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts