Question: 7. Consider a serial assembly line where the products move from activity A through D with the following throughput for each activity: Activity A: 500

7. Consider a serial assembly line where the products move from activity A through D with the following throughput for each activity:

Activity A: 500 units/day

Activity B: 300 units/day

Activity C: 800 units/day

Activity D: 450 units/day

Which activity is the bottleneck for this assembly line?