Question: 7. Consider a serial assembly line where the products move from activity A through D with the following throughput for each activity: Activity A: 500
7. Consider a serial assembly line where the products move from activity A through D with the following throughput for each activity:
Activity A: 500 units/day
Activity B: 300 units/day
Activity C: 800 units/day
Activity D: 450 units/day
Which activity is the bottleneck for this assembly line?