Question: 7 D Ltd is installing a state - of - the - art air traffic control system for National Aviation Authority. The work started on

7 D Ltd is installing a state-of-the- art air traffic control system for National
Aviation Authority. The work started on 1 July 2022 with an expected
finalisation date of 30 June 2025. The contract value is 4,000,000. The
agreed price is 4,000,000.
Expenses realised to 1,600,000.
Fifty percent job on the contract was completed.
Certificate of work finished have been issued by the engineering
department, to the value of 2,000,000.
Required
What is the contract profit in year 2023 and what have the carrying value
of the contract asset on 30 June 2023.
 7 D Ltd is installing a state-of-the- art air traffic control

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!