Question: (7) For Exercise B, if the project must be reduced a second time unit, which task(s) should be reduced? (8) For Exercise B, if the

(7) For Exercise B, if the project must be reduced a second time unit, which task(s) should be reduced?
(8) For Exercise B, if the project must be reduced a third time unit, which task(s) should be reduced?
(9)For Exercise B, what is the crash point?
(10)For Exercise B, what is the adjusted total cost at the crash point?
7. Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed, the adjusted total cost, and explain your choice if you have to choose between activities that cost the same. Note: Crash point of the network is the point in which the duration cannot be reduced any further. Total direct normal costs $550Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
