Question: 7. If -after a schedule update- the critical path changed, this can be attributed to (check all answers that apply): (2 Points) a) A change
7. If -after a schedule update- the critical path changed, this can be attributed to (check all answers that apply): (2 Points) a) A change in logic b) A change in the calendar of some activities c) A near-critical path became longer than the previous critical path d) A delay to an activity on the critical path