Question: 7 . If PV = 1 0 0 0 , EV = 1 2 0 0 , and AC = 1 3 0 0 ,
If PV EV and AC the project is:
a Ahead of schedule and under budget
b Ahead of schedule and over budget
c Behind schedule and over budget
d Behind schedule and under budget