Question: 7 . If PV = 1 0 0 0 , EV = 1 2 0 0 , and AC = 1 3 0 0 ,

7. If PV =1000, EV =1200, and AC =1300, the project is:
a. Ahead of schedule and under budget __________
b. Ahead of schedule and over budget
c. Behind schedule and over budget
d. Behind schedule and under budget