Question: 7. If you wanted the project shown below to be done in 78 days, what bonus would you offer per day to crash the project?

7. If you wanted the project shown below to be
7. If you wanted the project shown below to be done in 78 days, what bonus would you offer per day to crash the project? A=20 D=15 G-25 B=30 C=25 F=30 E=20 task Crash cost per normal time 20 Crash time 17 20 day A 30 B 25 10 normal cost 20000 30000 30000 20000 10000 15000 35000 Crash cost 26000 50000 37500 23000 22000 45000 44000 2000 2000 500 300 1200 D E 15 20 30 25 5 10 15 10 F 2000 600 G Bonus per day (work space if needed)