Question: 7. In the contracting method known as A+B, if the value of time is set by the owner as $15,000 | day, which contractor do

7. In the contracting method known as "A+B, if

7. In the contracting method known as "A+B, if the "value" of time is set by the owner as $15,000 | day, which contractor do you choose? Bidder Bid amount Days Bidder 1 $12,500,000 130 Bidder 2 $13,100,000 120 Bidder 3 $12,900,000 140