Question: 7 . Kool King Ltd . has six house air conditioning jobs to be processed through a two - step operation. The first operation involves

7. Kool King Ltd. has six house air conditioning jobs to be processed through a two-step operation. The first operation involves servicing of units, and the second involves installation. Processing times (in days) are as follows:
House
Operation 1 Operation 2
Archie 812
Bertrand 49
Cooper 117
Diaz 26
Edmond 125
Franz 12
a. Determine the sequence that will minimize the total completion time. [6]
b. What is the completion time? [6]