Question: 7 . Production manager after extensive analysis identified a product he believes should be handled in a work cell. Operations that are necessary are listed

7. Production manager after extensive analysis identified a product he believes should be handled in a work cell. Operations that are necessary are listed below. The customer expects delivery of 250 units per day and the workday is 420 minutes.
What is the takt time?
How many employees should be cross-trained for the cell?
Which operations may warrant special consideration?
Operation Time (min)
Shear 1.1
Bend 1.1
Weld 1.7
Clean 3.1
Paint 1.0