The following table refers to a project in which the objective is to raise capital for a commercial building activity.
ACTIVITY DURATION Days PREDECESSORS
A
B
C A B
D C
E C
F E
G C
H D E G
I G F
J H
K I, J
For parts a and b below you can use MS Project if you so desire. If you do so please cut and paste the relevant pages from MS Project do not send me the whole MS Project file
a Draw a network diagram of the project
b Identify the critical path, its duration and the activity slacks.
Consider the additional TimeCost tradeoff data.
ACTIVITY Normal Duration Normal cost Crash Duration Crash Cost
A $ $
B
C cannot crash
D
E
F
G
H
I
J
K
c Assume the overhead costs for this project are $ per day. What is the optimal crashing strategy? Please describe you crashing strategy stepbystep.
d What is the optimal project duration? What are the critical paths as a result of your crashing?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock