Question: 7 . You must find the payback for a project , and you have misplaced some of the information that you were given You know

 7 . You must find the payback for a project ,

7 . You must find the payback for a project , and you have misplaced some of the information that you were given You know that the project will generate positive cash flows of $60 000 per year at the end of each of the next 5 years , that its MPV is $75 , 100 , and that the company's WA CC is 10% . What is the project's regular payback ? Hin You must first find the project's cost , then use it to find the payback A . 254 years B . 2. 1 1 years C. 2.38 years D. 2.27 years 2. 45 years