Question: 705 - Leading Project - Strategic Tools & KPIs Wj Theron 56577 - Word (Product Activation Failed) REFERENCES MAILINGS REVIEW VIEW Aa ... 21 2.A.3.

705 - Leading Project - Strategic Tools & KPIs Wj Theron 56577 - Word (Product Activation Failed) REFERENCES MAILINGS REVIEW VIEW Aa ... 21 2.A.3. 9.3 AalbCcDc AaBbCcDc AaBb AaBbC AaBbcc 11 Normal 11 No Spac... Heading 1 Heading 2 Heading Paragraph Styles Exercise 4: (5 marks) 1) If the first quarter's forecast of a plant was 44 units per period, the actual quarter's demand was 45 units, and a = 0.12. What would be the second quarter's smoothing forecast? 2) Then if the actual second quarter demand turned out to be 47 units, what would be third quarter's forecast, using the same a? Please type your answer below. 44.47