Question: 7-2. Use the assignment method to determine the best way to assign workers to jobs, given the following cost information. Then compute the total cost
7-2. Use the assignment method to determine the best way to assign workers to jobs, given the following cost information. Then compute the total cost for your assignment plan. JOB
| A | B | C | D | E | ||
| 1 | 5 | 4 | 8 | 7 | 9 | |
| WORKER | 2 | 4 | 6 | 3 | 5 | 8 |
| 3 | 3 | 7 | 4 | 6 | 10 | |
| 4 | 2 | 5 | 5 | 8 | 5 | |
| 5 | 5 | 6 | 4 | 9 | 3 | |