Question: 7-3. Using Excel or Word, construct an AON diagram for the following AND determine (show) the critical path and indicate the duration of this project:
7-3. Using Excel or Word, construct an AON diagram for the following AND determine (show) the critical path and indicate the duration of this project:
| ACTIVITY | COMPLETION TIME (WEEKS) | IMMEDIATE PREDECESSOR |
| A | 7 | - |
| B | 8 | - |
| C | 5 | - |
| D | 8 | A |
| E | 4 | B |
| F | 7 | B |
| G | 6 | C |
| H | 10 | F |
| I | 9 | F, G |
| J | 5 | D, E |
| END | H, I, J |