Question: 79). When two or more resources are scheduled to do work at the same time in a project, they are said to be: Question 1

79).

When two or more resources are scheduled to do work at the same time in a project, they are said to be:

Question 1 options:

Incomplete

Crashing

In conflict

Inconvenienced

Question 2 (2 points)

Resources are associated with the following costs:

Question 2 options:

Fixed

Direct

Variable

Indirect

Both b and c

Question 3 (2 points)

When resources are constrained, they are first assigned to activities:

Question 3 options:

With the longest duration

With the least slack

With the highest risk

With the greatest execution difficulty

Question 4 (2 points)

When resources are applied to a draft schedule, it is likely that:

Question 4 options:

The schedule duration will be extended

The schedule duration will remain the same

The schedule duration will be less than originally thought

The schedule duration will include more slack

Question 5 (2 points)

Which of the following is not a project resource?

Question 5 options:

People

Equipment

Funding

None of the above

Question 6 (2 points)

The project budget is usually completed

Question 6 options:

Before activities are identified

After the WBS is created

After the project is started

After resources are assigned

Question 7 (2 points)

When the project is behind schedule, some options involving resources include:

Question 7 options:

Adding people to the project

Asking people to work longer hours

Outsourcing

Adding equipment to the project

All of the above

Question 8 (2 points)

If it is determined that additional resources are required late in the project, the impact to the project may include:

Question 8 options:

Increased project expenses

Increased management burden

Delays on some activities due to training requirements

All of the above

Question 9 (2 points)

A schedule is not a schedule until

Question 9 options:

The Gantt chart is created

The resources are added

The network diagram is analyzed

The project is chartered

Question 10 (2 points)

The largest portion of budgeted project costs come from:

Question 10 options:

Management

Materials

Indirect costs

Resources

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!