Question: 8 0 % Estimate ( days ) Max. duration ( days ) A 1 7 2 2 D 1 4 1 5 E 7 1

80% Estimate (days) Max. duration (days)
A 1722
D 1415
E 710
F 911
H 1418
For the above data for critical path with the precedence A-D-E-F-H, the recommended project duration for 90% confidence level using USM is? How many days?