Question: 8 2 points When the project team is dealing with threats, which risk response strategies will require more effort? Risk mitigation and risk acceptance Risk
points
When the project team is dealing with threats, which risk response strategies will require more effort?
Risk mitigation and risk acceptance
Risk escalation and risk mitigation
Risk avoidance and risk escalation
Risk avoidance and risk mitigation