Question: 8 3 . 4 % complete Question Following the start of a sprint, a key stakeholder constructed an email to a project team voicing displeasure
complete
Question
Following the start of a sprint, a key stakeholder constructed an email to a project team voicing displeasure of the work that just commenced, despite being inexperienced in agile. The stakeholder is insistent about changing the internal and external deliverables.
What next step should the project manager take?
ARequest the teams assessment of the matter at the next standup meeting.
BChange the backlog and comply with the stakeholders request.
CFacilitate a meeting with the product owner and the key stakeholder to align on deliverables.
DEncourage the stakeholder to participate in a discussion regarding backlog clarification.