Question: 8 3 . 4 % complete Question Following the start of a sprint, a key stakeholder constructed an email to a project team voicing displeasure

83.4% complete
Question
Following the start of a sprint, a key stakeholder constructed an email to a project team voicing displeasure of the work that just commenced, despite being inexperienced in agile. The stakeholder is insistent about changing the internal and external deliverables.
What next step should the project manager take?
A.Request the teams assessment of the matter at the next standup meeting.
B.Change the backlog and comply with the stakeholders request.
C.Facilitate a meeting with the product owner and the key stakeholder to align on deliverables.
D.Encourage the stakeholder to participate in a discussion regarding backlog clarification.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!