Question: 8 : 3 5 4 1 Time left 1 : 2 5 : 3 6 Match the Status Report term with each description: We have

8:35
41
Time left 1:25:36
Match the Status Report term with each description:
We have spent $2500 Choose.. as of today.
We have actually completed $1200 worth of work.
We are over budget by $100
As of today, what is the estimated value of work planned to be done. We should have done $100 worth of work by today.
Our project budget is $100,000
Choose...
Budget at Completion (BAC)
Cost Variance (CV)
Planned Value (PV)
Actual Cost (AC)
Earned Value (EV)