Question: 8 : 3 5 4 1 Time left 1 : 2 5 : 3 6 Match the Status Report term with each description: We have
:
Time left ::
Match the Status Report term with each description:
We have spent $ Choose.. as of today.
We have actually completed $ worth of work.
We are over budget by $
As of today, what is the estimated value of work planned to be done. We should have done $ worth of work by today.
Our project budget is $
Choose...
Budget at Completion BAC
Cost Variance CV
Planned Value PV
Actual Cost AC
Earned Value EV