8 children and 12 men complete a certain piece of work in 9 days. If each child
Fantastic news! We've Found the answer you've been seeking!
Question:
8 children and 12 men complete a certain piece of work in 9 days. If each child takes twice the time taken by a man to finish the work, in how many days will 12 men finish the same work ?
a. 8
b. 15
c. 9
d. 12