Question: 8) Design a layout using the following information. There are 6 tasks with the following predecessor and time requirements: Task Predecessor Time Required (min) A
8) Design a layout using the following information. There are 6 tasks with the following predecessor and time requirements:
Task Predecessor Time Required (min)
A None 5
B None 7
C None 9
D None 3
E B, D 8
G A, C 10
You need to complete 40 items per each 10 hour day. Use the line balance technique you learned using the Longest Processing Time to answer the following questions:
What is the cycle time?Round down to nearest integer.
What is the theoretical minimum number of stations?Round up to the nearest integer
At what station will D be completed?