Question: (8 point) In order to improve the system capacity, the management has studied the wheel assembly step. After improving the assembly method, the replacement time
(8 point) In order to improve the system capacity, the management has studied the wheel assembly step. After improving the assembly method, the replacement time for the assembly tool reduces from 20 minutes to 10 minutes, whereas the processing time per unit reduces from 1 minute to 0.5 minutes. What is the system capacityin scooters per hour after this improvement? If your answer is not an integer, provide at least three decimal places, e.g., 7.500. Hint:You need to check which step is the new bottleneck.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts