Question: 8 points How Did I Do ? table [ [ Activity , Duration ( weeks ) , Immediate Predecessor ( S ) ] ,
points
How Did I Do
tableActivityDuration weeksImmediate PredecessorSABACADAEAFBCGDEHFG
What is the overall duration of the project in weeks
weeks
What is the earliest week you could start activity FWrite the week number in the field below.
What is the earliest week you could finish activity G
What is the latest week you could start activity C
What is the latest week you could finish activity A
What is the slack time for activity B
Neeks
What would be the overall duration of the project if activity E were increased by weeks, from to weeks?
weeks
What would be the overall duration of the project if activity D were increased by weeks, from to weeks?
reeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
