Question: 8 points How Did I Do ? table [ [ Activity , Duration ( weeks ) , Immediate Predecessor ( S ) ] ,

8 points
How Did I Do?
\table[[Activity,Duration (weeks),Immediate Predecessor(S)],[A,1,-],[B,10,A],[C,5,A],[D,11,A],[E,4,A],[F,11,B,C],[G,9,D,E],[H,4,F,G]]
What is the overall duration of the project (in weeks)?
weeks
What is the earliest week you could start activity F?(Write the week number in the field below.)
What is the earliest week you could finish activity G?
What is the latest week you could start activity C?
What is the latest week you could finish activity A?
What is the slack time for activity B?
q, Neeks
What would be the overall duration of the project if activity E were increased by 2 weeks, from 4 to 6 weeks?
weeks
What would be the overall duration of the project if activity D were increased by 4 weeks, from 11 to 15 weeks?
reeks
 8 points How Did I Do? \table[[Activity,Duration (weeks),Immediate Predecessor(S)],[A,1,-],[B,10,A],[C,5,A],[D,11,A],[E,4,A],[F,11,B,C],[G,9,D,E],[H,4,F,G]] What is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!