Question: 8 * * * * Question: * * What does the acronym WBS stand for in project management? A ) Work Breakdown Schedule B )

8**** Question:** What does the acronym WBS stand for in project management?
A) Work Breakdown Schedule
B) Work Breakdown Structure
C) Work Breakdown System
D) Work Breakdown Scope
 8**** Question:** What does the acronym WBS stand for in project