Question: 8. The following precedence network is used for assembling a product. You have been asked to achieve an output of 240 units per eight-hour day.

8. The following precedence network is used for
8. The following precedence network is used for assembling a product. You have been asked to achieve an output of 240 units per eight-hour day. All times in this network are in minutes. Balance the line using the following rules assign tasks to workstations on the basis of most following tasks (Rule 1). Use greatest positional weight (Rule 2) as a tiebreaker. What is the third activity assigned to workstation 17 0.2 04 02 12 b 04 1.0 20 Select one: b. None of the provided options ca d. d