Question: 8) Using the information provided below, construct a network activity diagram (5 pts) and answer the following questions: a) Conduct a forward and backward pass
8) Using the information provided below, construct a network activity diagram (5 pts)
and answer the following questions:
a) Conduct a forward and backward pass using AON notation. What is the estimated total duration for the project? (2 pts)
b) Identify all paths through the network. Which is the critical path? (3 pts)
c) Which activities have slack time?(2 pts)
Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
I want an BOX Network Diagram with the Calculations.
Thanks!

Activity Description Predecessors Duration (Days) A Site Selection None 4 B Buy Food & Drinks A 6 C Rent Facilities A D Build Seating A 6 E Electrical installation C 4 F Security Preparation B 6 G Lighting installation E 4 H Sound system installation E, F Build the Stage D 6 Tear down G, H, I 3