Question: 8.29 The fixed and variable costs (in U.S. dollars) for the new recycling plant that Eldon Yi is opening in Australia are computed as follows:

8.29 The fixed and variable costs (in U.S. dollars) for the new recycling plant that Eldon Yi is opening in Australia are computed as follows: Cost Victoria Perth Fixed $1,000,000 $800,000 Variable $73/unit S112 unit a) Over what range is each city preferable? b) For a recycling of 5,000 units, which site is best