Question: 83. Process of decomposing deliverables into smaller, more manageable components is complete when: A. Project justification has been established B. Change requests have occurred C.

83. Process of decomposing deliverables into smaller, more manageable components is complete when:

A. Project justification has been established

B. Change requests have occurred

C. Cost and duration estimates can be developed

D. Each work element can be found in the WBS