Question: 8-3 (Restaurant work scheduling problem) The famous Y. S. Chang Restaurant is open 24 hours a day. Waiters and busboys report for duty at 3a.m.,
8-3(Restaurant work scheduling problem)The famous Y. S. Chang Restaurant is open 24 hours a day. Waiters and busboys report for duty at 3a.m., 7a.m., 11a.m., 3p.m., 7p.m., or 11p.m., and each works an 8-hour shift. The following table shows the minimum number of workers needed during the six periods into which the day is divided. Chang's scheduling problem is to determine how many waiters and busboys should report for work at the start of each time period to minimize the total staff required for one day's operation. (Hint:LetXiXiequal the number of waiters and busboys beginning work in time periodi, wherei=1,2,3,4,5,6.i=1,2,3,4,5,6.)
PERIOD
TIME
NUMBER OF WAITERS AND BUSBOYS REQUIRED
1
3a.m.-7a.m.
3
2
7a.m.-11a.m.
12
3
11a.m.-3p.m.
16
4
3p.m.-7p.m.
9
5
7p.m.-11p.m.
11
6
11p.m.-3a.m.
4
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts