Question: 8A high-level manager in an organization would like to use a critical project resource for a new project. Which action should the project manager take?
8A high-level manager in an organization would like to use a critical project resource for a new project. Which action should the project manager take? SELECT THE CORRECT ANSWER Contact the program manager to resolve the issue Request that the high-level manager provides a replacement Use the legitimate form of power to reject the request Tell the team and reassign that resource's responsibilities to other team members
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock