A firm uses a serial assembly system and needs answers to the following:
An output of 900 units per shift (8.00 hours) is desired for a new processing system. The system requires product to pass through four stations where the work content at each station is 24 seconds. What is the required cycle time for such a system?
Note: Round your answer to the nearest whole number.