Question: 9 . 1 7 Consider the following project tasks and their identified best, likely, and worst - case estimates of task duration. Assume the organization
Consider the following project tasks and their identified best, likely, and worstcase estimates of task duration. Assume the organization you work for computes TE based on the standard beta distribution formula. Calculate the TE for each of the following tasks round to the nearest integer:
tableActivityBest,Likely,Worst,TEABCDEFGHIJ
Using the Description and Predecessors information from problem and the calculated TE as the duration in days, construct the network activity diagram based on the following
Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?
Identify all paths through the network. Which is the critical path?
Which activities have slack time?
Identify all burst activities and merge activities.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
