Question: 9. (1 point) Please choose the MOST correct alternative. a. If the discount rate used for a project with normal cash flows is equal to

 9. (1 point) Please choose the MOST correct alternative. a. If

9. (1 point) Please choose the MOST correct alternative. a. If the discount rate used for a project with normal cash flows is equal to its IRR, then the PI=1. b. The NPV of a project is equal to zero when the discount rate used is the IRR. c. For a project with normal cash flows, the PI will always be greater than 1 if the NPV is positive. d. The decision regarding acceptance / rejection of a project should be based on the NPV criterion. e. All of the above are correct