Question: 9 . 1 : Project Scheduling Based on Expected Activity Times Consider the following project network and activity times ( in weeks ) :

9.1: Project Scheduling Based on Expected Activity Times
Consider the following project network and activity times (in weeks):
\table[[Activity,A,B,C,D,E,F,G,H],[Time,6,6,8,5,6,2,10,7]]
a. Identify the critical path.
B-E-G?