Question: 9. 19 An advertising project manager has developed a program for a new advertising campaign. In addition, the manager has gathered the time information for

9. 19 An advertising project manager has developed a program for a new advertising campaign. In addition, the manager has gathered the time information for each activity as shown in the following table: Time Estimates (week) Optimistic Most Likely Pessimistic Immediate Predecessor(s) A 7 2 10 3 9 B 14 D E B 8 a Calcu gia the expected at times round to nearest Integer Cate the activity sacks. What is the folal-project length? Make sure you fully label all nodes in the newark et the entical path what are the alternative paths and how muon si lime is associated with each mon-chical bath To Dans what is the mood of the project fshing on week 247