Question: 9 . 7 Subbase Thickness. A flexible pavement is to be designed. The moisture factor is 1 . 0 . The subgrade has been prepared

9.7 Subbase Thickness. A flexible pavement is to be designed. The moisture factor is 1.0. The
subgrade has been prepared to a CBR of 5. The structural coefficient for the 2-incb hot mix as-
phalt is 0.4, and there should be 6 inches of asphalt base with a structural coefficient of 0.3. The
structural coefficient of the subbase =0.10. The reliability is 90 percent, standard deviation is
0.4, and 20,000,000 ESAL are expected. The PSI when built was 4.8 and the PSI before rehabili-
tation is to be no less than 2.3. How much subbase aggregate is required? Express your answer in
inches of subbase thickness.
9.8 Suhbase Thickness-Drainage Problems. For the previous problem, if there is a high
amount of water and difficult drainage and m is 0.65 for the subbase, how much subbase aggre-
gate is required? (Hint: m1=m2=1.)
Please answer 9.8 and not 9.7. The answer of 9.7 is 24 inches of subbase aggregate is required. Thank you!
9 . 7 Subbase Thickness. A flexible pavement is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!