Question: 9 A construction project is broken down into the following 10 activities: a. Draw the network diagram. b. Find the critical path. c. If activities
9 A construction project is broken down into the following 10 activities: a. Draw the network diagram. b. Find the critical path. c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities. would you shorten to cut the project by four weeks