Question: 9 . Circulating Water System responsible for? Maintaining Vacuum Maintaining Hot - well Level Creating Vacuum CEP Bearing Cooling 1 0 . What is the
Circulating Water System responsible for?
Maintaining Vacuum
Maintaining Hotwell Level
Creating Vacuum
CEP Bearing Cooling
What is the minimum LDO tank level before starting LDO system?
LDO Tank LVL m
LDO Tank LVL m
LDO Tank LVL m
LDO Tank LVL m
Boiler Fill Pump supply water to:
Condenser Quick Filling, Boiler Initial filling, Deaerator initial Filling
Condenser Quick Filling & Boiler Initial filling
Condenser Quick Filling & Deaerator initial Filling
Condenser Quick Filling, Boiler Initial filling, Deaerator initial Filling & DM Makeup tank
Initially fill Separator upto normal level ie
mmwc
mmwc
mmwc
mmwc
What are the sources of charging Auxiliary Steam Header ASH
Auxiliary Boiler, CRH Line, Boiler Primary SH
Auxiliary Boiler, Boiler Primary SH Adjacent Unit Auxiliary Steam Header
Auxiliary Boiler, CRH Line, Adjacent Unit Auxiliary Steam Header
Auxiliary Boiler, CRH Line, Boiler Primary SH Adjacent Unit Auxiliary Steam Header
What is the source of steam for Mill Steam Inerting System?
Cold Reheat CRH
Auxiliary Steam Header ASH
No Extraction
Boiler Primary SH
What is the correct sequence for starting Generator Seal Oil System?
Gen Vapor Extraction Fan, Air Side Seal Oil Pump, H Side Seal Oil Pump, Gen. Gland
Seal Float Pump
Gen Vapor Extraction Fan, Side Seal Oil Pump, Air Side Seal Oil Pump, Gen. Gland
Seal Float Pump
Gen Vapor Extraction Fan, Gen Gland Seal Float Pump, Air Side Seal Oil Pump, Side
Seal Oil Pump
Gen. Gland Seal Float Pump, Gen Vapor Extraction Fan, Air Side Seal Oil Pump,
Side Seal Oil Pump
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock