Question: 9. Given the time-phased work packages and network, complete the baseline budget form for the project. Market Surwey Project WBS Work Package Cost by Week

9. Given the time-phased work packages and network, complete the baseline budget form for the project. Market Surwey Project WBS Work Package Cost by Week WP Design 42 WP Survey 2 2 4 4 4 5 WP Report 3 3 2 Project Network Report Design Survey Time-Phased Budget Week Task Budget Design 15 2 Survey Report 21 the 40 Total Cumulative