Question: 9 . If a project criterion indicates that the project must meet a specific date, that criterion is classified as A . Constrained B .
If a project criterion indicates that the project must meet a specific date, that criterion is
classified as
A Constrained
B Enhanced
C Accepted
D Limited
E Fixed
The lowest element in the hierarchical breakdown of the WBS is
A A deliverable
B A work package
C A cost account
D A lowest sub deliverable
E An object
The process of forecasting or approximating the time and cost of completing project
deliverables is called
A Budgeting
B Predicting
C Estimating
D Planning
E Guesstimating