Question: 9 please help me You have a project with a budgeted cost of 300,000 USD. So far you have spent 100,000 USD and the value
9
please help me
You have a project with a budgeted cost of 300,000 USD. So far you have spent 100,000
USD and the value of the completed work is 80,000 USD. However, as per the schedule
you should have earned 90,000 USD to date.
Client is insisting to complete the
project on time. Calculate the Estimate
at Completion (EAC).